Due to the weather, utility work on the north side of the project has halted after completing work to get out of the intersection between 3rd Street N and Market Street. Utility work on the south side of the project did not start today.

The contractor will continue to place aggregate at the intersection of Market Street and 4th Street N and fill 3rd Street S with sand today. Though 3rd Street S will have sand, it will not be drivable until aggregate has been placed on top later this week. Residents on 3rd Street S and 4th Street S, north of Minnesota Street, should continue to use alley access to your properties. Millings have not yet been removed south of Minnesota Street, leaving these streets accessible.

The contractor will monitor weather conditions regarding when work will start again. The contractor will have someone on-site tomorrow morning to ensure garbage is collected. It is more likely that work will resume on Wednesday as rain/snow stop.