GM contracting has mobilized their equipment with anticipation of installing sanitary sewer on the remaining block of 3rd Street S, between the levee and Main Street. This work would have started today, but was delayed due to forecasted rain in the afternoon. While the plan is to start this work tomorrow, that could still change depending on weather this week. More information will be provided when known.

Curb and gutter left in-place over winter was significantly removed yesterday so the contractor can complete the remaining street construction in preparation of new curb and gutter installation. The contractor currently has concrete crews scheduled for the week of April 19th.

Dominic Metzger will be on-site during construction. He can be contacted at 507.514.7312 with questions.